...

Second Shah Deniz 2 platform jacket sent offshore (PHOTO)

Oil&Gas Materials 16 March 2017 13:15 (UTC +04:00)
The Shah Deniz consortium has announced the sail away of the second jacket for the Shah Deniz Stage 2 platforms.
Second Shah Deniz 2 platform jacket sent offshore (PHOTO)

Baku, Azerbaijan, Mar. 16

Trend:

The Shah Deniz consortium has announced the sail away of the second jacket for the Shah Deniz Stage 2 platforms.

The Quarters and Utilities (QU) platform jacket sailed away to the Shah Deniz contract area in the Caspian Sea from the Heydar Aliyev Baku Deepwater Jackets Factory (BDJF) ahead of schedule on March 15, said the consortium in a message.

“The transportation, launch, positioning, pile installation and final completion activities of the jacket structure are expected to take around 75 days, depending on the prevailing weather conditions,” said the Shah Deniz consortium.

The construction of the jacket was completed ahead of schedule on February 20 and was then successfully loaded onto the transportation barge STB-1 at the quayside of BDJF.

“The QU platform jacket, built by the BOS Shelf, Star Gulf and Saipem consortium, was fully constructed in the country at the BDJF, using local construction infrastructure and facilities.”

The Shah Deniz consortium said 2,000 people, including subcontractors and specialist vendors were involved in the construction works, and some 90% of the construction workforce was Azerbaijani citizens.

“The second jacket sail away is the first major milestone planned for this year and we are pleased to have achieved it ahead of schedule. 2017 is an important year for BP and for the Shah Deniz 2 project, which is already around 90% complete. We have planned a series of key completion milestones for this year. We are committed to achieving all of these milestones on schedule to make BP’s 25th anniversary celebrations in Azerbaijan a big success,” Ewan Drummond, Shah Deniz 2 Projects vice-president, said.

“On this occasion, I would like to thank SOCAR and our partners for their support and cooperation in moving this giant project forward. My thanks are also to all people representing BP, contractors and subcontractors whose hard work has made it possible to achieve this milestone ahead of schedule. I would like to specifically thank the BOS Shelf, Star Gulf and Saipem

consortium for their firm commitment to BP’s safety standards throughout the 22-month construction period of this jacket. This is a great safety achievement and I am confident that the offshore installation will be performed with the same level of commitment to safety and quality,” Drummond said.

The QU platform jacket weighs approximately 12,084 tons and stands 105 meters high. It contains 31 J Tubes, 7 utility caissons and 3 J tube caissons. The jacket will be installed in a water depth of 95 meters.

Tags:
Latest

Latest