AZERGAZNEGL PLANS TO REPAIR GAS PIPELINES AGSU-KYURDEMIR AND GARADAG-TBILISI

Oil&Gas Materials 15 August 2005 16:38 (UTC +04:00)

Unsealing of tender bids for capital overhaul of the gas line Agsu-Kyurdemir (L-4,26 km, D-325 mm) and the gas pipe line Garadag-Tbilisi (L-0,8 km, D-720 mm) was held at the Azergazneql Ptoduction Unit (PU), a structure of JSC Azergaz, PU told Trend.

Capital repairing of the gas pipeline sections Agsu-Kyurdemir: 10,7-13 km, 14,3-14.7 km, 18,7-20 km, 20-20,3 km is envisioned. The capital overhaul of Garadag-Tbilisi section will be carried out on the crossing of the Djeyrankechmyaz river.

Per 3 companies took part in each lot. "The tender commission is currently assessing the bids. The winner is expected to select in the shortest time. Repair works are planned to commence in late Augus”, PU noted. 60 days are allocated for performing works on each lot.