AZERENERJI RESTORES ENERGY SUPPLY TO 6 SOUTHERN DISTRICTS

Oil&Gas Materials 30 September 2005 13:34 (UTC +04:00)

Azerenerji Joint Stock Company (JSC) restored the energy supply to 6 southern regions of Azerbaijan after the yesterday’s incident, Trend reports quoting Etibar Pirverdiyev, the head of Azerenerji, assaying on Friday.

According to Pirverdiyev, the incident to place on Thursday evening at 20:34pm in the third Masally energy transmission line, running via the territory of Jalilabad District. As a result, the energy supply to Lankaran, Astara, Lerik, Jalilabad, Sabirabad, and Salyan was ceased.

“Within 11 minutes of the accident the energy supply to all regions was restored, but Lerik. The energy supply was implemented through 110 KW ETL. After an hour we revealed the place of incident. At 7:30am the third Masally ETL was rehabilitated. At present the work on revealing the reasons of the incident is underway.

“Perhaps, there is a human factor, as the inspection of the damaged cable showed that a fire could cause the incident. At present the documents for appeal to the law-enforcement bodies of the country are being prepared,” Pirverdiyev underlined.

Latest

Latest