Tashkent, Uzbekistan, Nov. 11
By Demir Azizov- Trend:
Uzbekenergo JSC, including the largest power stations of Uzbekistan, has announced a tender for overhaul of a hydraulic generator No 4 with a capacity of 18 megawatts (the Chirchik hydropower station).
The work must be conducted up to February 29, 2016.
The repair work will be carried out at the expense of the customer - "Chirchik Cascade of Hydropower Stations".
The tender documents will be received till December 21, 2015.
All documents are available at: 111700, 2A D. Rozit str., Chirchik town.
Telephone: (0-370) 71-6-10-22.
Fax: (0-370) 71-6-10-21.