Azerbaijan, Baku, Feb.23 / Trend /
In January, the Azerbaijani thermal power plant (TPP) generated 64.4 million kilowatt hours of electricity compared to forecasted 64 million kilowatt hours, the JSC Azerenergy (production and distribution of electricity in the Azerbaijani regions) reported today.
According to the report, repair work has been successfully carried out at the plant. As a result, technical and economic parameters of power units have improved. At present, the thermal power plant operates in accordance with the dispatching schedule.
Reconstruction work on the first power unit has been completed and the unit is connected to the network. A similar work has been started on the seventh unit. Currently, four power units are in operation at the plant and 16-18 million kilowatt hours of electricity is generated every day. Three power units are set aside as reserve.