...

Expression of interest for construction of hydroelectric power plant in Georgia

Oil&Gas Materials 20 June 2014 19:25 (UTC +04:00)

Tbilisi, Georgia, June 20

By Nana Kirtzkhalia - Trend:

Georgia's Energy Ministry has announced an expression of interest for feasibility studies, constructing, owning and operating the hydroelectric power plant on the Didkhevi River in Kakheti Region (eastern Georgia).

The ministry said on June 20 that the plant's installed capacity will be 1.3 megawatt, and generation capacity - seven million kWh.

The estimated project cost is $2,301,000.

Applications for the expression of interest will be accepted until August 1, 2014, 18:00 (local time).

Edited by CN

Tags:
Latest

Latest