bp completes subsea structure, spools installation engineering works for ACE project

Oil&Gas Materials 11 August 2021 15:34 (UTC +04:00)

BAKU, Azerbaijan, Aug.11

By Leman Zeynalova - Trend:

The subsea structure and spools installation engineering works were completed in the second quarter as part of the Azeri Central East (ACE) project, Trend reports with reference to bp.

Despite the challenges and restrictions caused by the pandemic, the Azeri Central East project remained resilient during the first half of the year along with the other bp-operated activities.
The shipment of major equipment packages and bulk materials to Baku continued in support of the fabrication schedule.

Fabrication activities on the topsides and drilling facilities continued at the fabrication yard in Bibi-Heybat. These included progressing the drill floor fabrication on the drilling equipment support module, mechanical package installation, pipe fabrication, erection and cable pulling. The skid deck rail machining commenced. The living quarters modules were delivered to Baku and offloaded at the yard, with the first three modules already lifted.

At the Heydar Aliyev Baku Deepwater Jackets factory (BDJF) the jacket fabrication continued at multiple work fronts. Welding of the centre box frames progressed, preparation for the jacket skidding commenced. During the second quarter, the project also progressed the offshore installation works associated with the spare power scope on the East Azeri platform, to allow the ACE platform to draw power from the Azeri field optimising power generation across the assets.

At the Sangachal terminal, the design of the onshore control room was completed allowing to commence the planned modifications in the fourth quarter.

Overall, the engineering, procurement and fabrication works remain on track to support first production from the ACE project in 2023.

---

Follow the author on Twitter: @Lyaman_Zeyn