BAKU, Azerbaijan, January 25. Uzbekneftegaz JSC completed repair work at well No.51 of the Kulbeshkak field (the country’s Bukhara region), Trend reports citing the press service of the company.
The Kulbeshkak field was put into operation in 2008.
As a result, an industrial gas flow of 60,000 cubic meters of gas and 1 ton of gas condensate per day was obtained.
A perforation of well No.51 was carried out (1859-1854 meters).
Earlier in January 2023, Uzbekneftegaz JSC completed drilling at well No.26 of the Kuyi Surgil field (the Republic of Karakalpakstan). As a result, an industrial gas flow of 820,000 cubic meters of gas and 1 ton of gas condensate per day was obtained.