Major events in Caspian countries' oil and gas industry for last week (Jan.19-23)

Analysis Materials 27 January 2015 10:59 (UTC +04:00)

Drilling of new wells being completed within Shah Deniz-2 project in Azerbaijan

All the work on drilling of SDC-04 well, the project depth of which exceeds 6,000 meters, will be completed in the next few weeks as part of pre-drilling on the second stage of the development of Shah Deniz gas condensate field in the Azerbaijani sector of the Caspian Sea.

The drilling of SDD-03 well, the project depth of which is about 6,300 meters, is planned to be completed in the next few months within the framework of the Shah Deniz-2 project, according to the source.

The number of the drilled wells will reach eight after the completion of the work on SDC-04 and SDD-03 wells.