Projection of Shaki module power station complete

Oil&Gas Materials 21 December 2005 15:08 (UTC +04:00)

Projection of the Shaki module power station is complete, Azerenerji JSC told Trend.

According to Marlen Asgarov, the Vice President of the company, it will enable to carry out land work. In particular, Globus company is implemented a set of geodesic, geologic and topographic researches. Part of analysis is currently being carried out in relevant laboratories.

A foundation of the building has been laid, while the carcass of the ground floor is under construction. Finland will supply sketches for different floors of the building. 30 containers with equipment and details to be used during the foundation laying were delivered by rail. The rest 45 containers will be delivered as required.

The Shaki module power station is comprised of 10 module blocs with the general capacity of 87 MW. Energy to be generated through 110kW substation will delivered to the unified energy system.