Opening of purpose-build facility within Shah Deniz 2 postponed

Oil&Gas Materials 1 November 2017 13:12 (UTC +04:00)

Baku, Azerbaijan, Nov.1

By Leman Zeynalova – Trend:

The new purpose-built facility within the second stage of development of Azerbaijan’s Shah Deniz field is expected to be commissioned by UK EXPRO international oilfield service company during November, the company's manager for Azerbaijan Andy Sadler told Trend.

“There have been some delays in the commissioning and we are now hoping that this will be done during November so that we can then move into the facility in December,” he said.

Earlier, Sadler said the facility is expected to be commissioned by the end of October.

The new facility has been constructed to enable EXPRO to deliver its products and services to clients operating within the Caspian region.

“Our long term plans are to build the business in Azerbaijan which the new facility is a key part of. This state of the art facility will demonstrate our commitment to our existing and potential clients,” added Sadler.

EXPRO has had a presence in the Caspian region since 2007, when it was awarded a contract to supply completion landing strings for Azerbaijan's Azeri-Chirag-Gunashli block of fields.

In 2014, EXPRO was awarded the contract to build landing strings for Azerbaijan's Shah Deniz Stage 2.

As part of the Shah Deniz 2 project, gas production will increase from 9 to 25 billion cubic meters per year. The produced gas will be exported to Turkey and the European markets through the expansion of the South Caucasus Pipeline and the construction of the Trans-Anatolian (TANAP) and Trans-Adriatic (TAP) gas pipelines.

A contract for development of the Shah Deniz offshore field was signed on June 4, 1996. The field's reserve is estimated at 1.2 trillion cubic meters of gas.

---