Iran to launch 6 platforms in South Pars gas field

Oil&Gas Materials 24 June 2016 17:20 (UTC +04:00)

Baku, Azerbaijan, June 24

By Emil Ilgar – Trend:

Iran is preparing to launch six platforms in the giant South Pars gas field by March 2017.

The platforms 14A (first platform of the phase 14), 17B, 18B, 19A, 20A and 21A are projected to be installed in the field.

In total, Iran is projected to add 100 million cubic meters of gas per day to the current 431 million cubic meters per day production capacity of South Pars by March 2017, said Ali Akbar Shabanpour, managing director at Pars Oil and Gas Company, SHANA reported June 24.

He added that the platforms 13A and 13B are also projected to be installed in the next fiscal year, which will start on March 21, 2017.

Iran plans to produce 700 million cubic meters of gas per day from South Pars field, when all of phases become operational (except for phase 11) by 2019.

Progress at South Pars phases

Phases

March 2016 (%)

Million cubic meters per day at plateau

Phases 1-10

100

250

Phase 11

0

50

Phase 12

90.6

82

Phase 13

75.9

50

Phase 14

61.8

50

Phases 15-16

98.4

50

Phases 17-18

93.4

50

Phase 19

92

50

Phases 20-21

85.7

50

Phases 22-24

80.2

75

Total

-

757

Source: Iran Oil Ministry