1.2m euros spend within 1st stage of project on SCADA application

Oil&Gas Materials 23 September 2005 18:43 (UTC +04:00)

“The Siemens has spend 1.2 euros within the 1st stage of the project on application of SCADA system,” Samir Akhundov, the Director General and head of Baku representative office of the Company, told Trend.

According to Akhundov, the value of the project comprises 1.5m euros. “We delivered all necessary devises from Berlin and will install them in a month,” he added. The 1st stage of the project envisages establishment of Central Control Department.

Akhundov underlined that the Company also intended to participate in the tender on implementation of the 2nd stage of the $48m project, which will be financed by the World Bank.