Baku, Azerbaijan, Jan. 19
By Maksim Tsurkov – Trend:
Azerbaijan Railways CJSC has launched the next stage of work for overhaul of the Baku-Boyuk Kasik railway, Sevinj Gadirova, head of the press service of Azerbaijan Railways CJSC, told Trend Jan. 19.
She said that the overhaul of the 7.8-km Tovuz-Govlar section began on Jan. 19.
The reconstruction work will last five days, she added.
The project to reconstruct the 600-km Baku-Boyuk Kasik railway started in October 2015.
To date, 435 kilometers of the railway have been reconstructed.