The construction work at the Sumgayit power station carried out by German is
under schedule. “The work focused on foundation laying under turbine, the press service of Azerenerji told Trend.
Besides, they carried out serious work on construction of water intake and water colling systems, as the depth of the sea exceeds 2.5 meters that excludes possibility to use ordinary methods of water intake and water cooling. The experts of the German Ingros-Lackner were invited to solve the problem. They visited Sumgayit to get necessary information and presented several projects on construction of dam.