Power plants of Azerbaijan’s Azerenergy JSC generated 2.123 billion kilowatt hours of electricity in January 2018 as compared to 2.164 billion kilowatt hours in the same period of 2017.
Electricity generation slightly down in Azerbaijan

Baku, Azerbaijan, Feb. 5

By Maksim Tsurkov – Trend:

Power plants of Azerbaijan’s Azerenergy JSC generated 2.123 billion kilowatt hours of electricity in January 2018 as compared to 2.164 billion kilowatt hours in the same period of 2017, says a message from the company.

The message says that in general, 21.9 billion kilowatt hours of electricity was generated by power plants of Azerenergy in 2017 as compared to 22.6 billion kilowatt hours in 2016.

The generation capacity of the power system of Azerbaijan is 7,172.6 megawatts, which makes it possible to generate about 24 billion kilowatt hours of electricity per year. This enables Azerbaijan to annually export 2.1 billion kilowatt hours of electricity.

---