...

Turkish company updates on construction of TANAP compressor stations

Oil&Gas Materials 17 September 2018 12:23 (UTC +04:00)

Baku, Azerbaijan, Sept.17

By Leman Zeynalova - Trend:

Construction of the compressor stations as part of the Trans Anatolian Natural Gas Pipeline (TANAP) is 82 percent complete, Deputy General Director for Internal Projects of the Turkish Tekfen Holding Mustafa Kopuz told Trend.

Tekfen is the contractor of TANAP’s Lot 3, envisaging construction of the pipeline from Sivas to Eskisehir in Turkey, as well as for construction of compressor and metering stations.

TANAP Compressor Stations Phase 1 construction work is 70 percent complete, according to Kopuz.

A ceremony to launch TANAP took place June 12 in the Turkish city of Eskisehir.

TANAP, together with Trans-Adriatic Pipeline (TAP), is a part of the Southern Gas Corridor, which provides for the transportation of gas from the Azerbaijani field Shah Deniz to Europe.

The initial capacity of TANAP is expected to be 16 billion cubic meters of gas per year. About six billion cubic meters will be supplied to Turkey, and the rest to Europe. After completion of the TAP, the gas will reach Europe in early 2020.

The share distribution in TANAP is as follows: Southern Gas Corridor CJSC - 51 percent, SOCAR Turkey Enerji - 7 percent, Botas - 30 percent, and BP - 12 percent.

The launching ceremony of the first stage of the Southern Gas Corridor project was held in Baku on May 29.

The gas from the Azerbaijani Shah Deniz field has already gone through the first segment of the Southern Gas Corridor - from the Sangachal terminal to the expanded South Caucasus Pipeline.

The Southern Gas Corridor, which costs more than $40 billion, is one of the priority projects for the EU and provides for the transportation of 10 billion cubic meters of Azerbaijani gas from the Caspian region through Georgia and Turkey to Europe.

---

Follow the author on Twitter: @Lyaman_Zeyn

Tags:
Latest

Latest