President of the Republic of Azerbaijan Ilham Aliyev attended the opening of Avtovagzal and Memar Ajami stations of the new violet line of Baku Metro April 19.
Azerbaijani president attends opening of new metro stations in Baku

Baku, Azerbaijan, April 19

Trend:

President of the Republic of Azerbaijan Ilham Aliyev attended the opening of Avtovagzal and Memar Ajami stations of the new violet line of Baku Metro April 19.

The large-scale landscaping work was carried out, and green areas were laid out around Avtovagzal station.

Zaur Huseynov, chairman of Baku Metro CJSC, informed the president about the conceptual development scheme of the Baku Metro lines.

The conceptual development scheme envisages the expansion of the existing infrastructure in phases by 2030, and the creation of a huge underground transport network. Baku Metro will consist of five lines, 76 stations and 119 km-long network of underground tunnels. Some 53 new metro stations will be built until 2030.

The president cut the ribbon symbolizing the opening of Avtovagzal station, and reviewed the conditions created here.

The construction of the station started in September 2009.

The station consists of the platform, two vestibules, eight exits, ventilation point and two pyramids.

The total length of the station is 560 meters. An elevator was installed here for people with disabilities.

President Aliyev then arrived at Memar Ajami station by train.

The total length of the station is 168,5 meters. There are three exits and an elevator for people with disabilities.