Oil&Gas Materials 25 October 2005 19:02 (UTC +04:00)

The first large equipment consignment for the Astara Module Power Station (MPS) arrived in Baku from Finland, Trend reports referring to the news release of the Azerenerji press service.

The 36 containers consist of details and accessories to be assembled in Astara. Besides, the ships delivered large-tonnage generators, which will be unloaded soon.

According to Mehdi Ismayilov, the Director of the Astara MPS, the work carried out under the confirmed schedule and the energy object will be ready by late 2005.

The station consisted of 10 modules per 8.7 MW/H will come as the first from 52 module stations to be constructed by the Azerenerji JSC from 2005 to 2006.