Eriell Group completes commissioning of wells, construction of pipelines in Uzbekistan

Oil&Gas Materials 14 September 2021 13:09 (UTC +04:00)
Eriell Group completes commissioning of wells, construction of pipelines in Uzbekistan

BAKU, Azerbaijan, Sept. 14

By Fakhri Vakilov – Trend:

The international oil service group Eriell Group has commissioned well No. 58 of the Khojikazgan field of the Gazli oil and gas production department in the Bukhara region of Uzbekistan, Trend reports citing the press service of the company.

The construction of a gas pipeline loop with a diameter of 108x8 mm and a total length of 2,336 linear meters was completed. The planned drilling period was 70 days. The ERIELL Group team of specialists employed in this field coped with the task 10 days ahead of schedule.

In addition, at the facilities of the Mubarek oil and gas production department in the Kashkadarya region, work was completed on the power supply of electrochemical protection means (construction of an overhead line) with a length of 3.1 km within the project "Construction of a gas pipeline with a diameter of 530x10 mm from the BVN-5" Zevardy "- UKPG- Zevardy "gas pipeline to the BVN- gas pipeline 8p "Zevards" - DKS-2 "Zevards".

Moreover, work was completed on the power supply of ECP facilities (construction of overhead lines) with a length of 1 km of the facility "Construction of a gas pipeline with a diameter of 1020x11 mm from Gas pretreatment unit -1" Samantepe "to Gas pretreatment unit -2" Samantepe "and connected to the electrochemical protection facilities of wells No. 309, No. 312, No. 314 of the field "Zewards".

---