BP names time of starting production on Azeri Central East oil platform

Oil&Gas Materials 7 October 2022 16:09 (UTC +04:00)
BP names time of starting production on Azeri Central East oil platform
Sadraddin Aghjayev
Sadraddin Aghjayev
Read more

BAKU, Azerbaijan, October 7. Oil production on the Azeri Central East (ACE) platform in Azerbaijan is planned to start since 2024, BP’s Project Manager for the platform Neal Phillips told reporters, Trend reports.

According to Phillips, in the first quarter of 2023, it’s planned to begin installation of the lower part of the ACE platform.

"The upper part of the platform is still under construction. After installing the lower part and preparing the upper part, we’ll proceed with the installation of the upper part. Then we expect to start developing the field in the late 2023-early 2024," he added.

The Azeri Central East (ACE) project is centered on a new 48-slot production, drilling and quarters platform located mid-way between the existing Central Azeri and East Azeri platforms in a water depth of approximately 140 meters.

The project will also include new infield pipelines to transfer oil and gas from the ACE platform to the existing ACG Phase 2 oil and gas export pipelines for transportation to the onshore Sangachal Terminal.

In addition, there will be a water injection pipeline installed between the East Azeri and ACE platforms to supply injection water from the Central Azeri compression and water injection platform to the ACE facilities.