Shaki module power station to become 2nd of its type in Azerbaijan

Oil&Gas Materials 19 December 2005 14:31 (UTC +04:00)

Upon completion of the construction of the Astara module power station the technique will be attracted to the construction of the Shaki module power station, Azerenerji joint stock company told Trend.

According to the Director of AZENCO, Javid Shahbuzov, within a week several generators of the Astara module power station will be connected and tested and on the eve of 2006 the energy will enter the energy system.

The construction of the module power station in Shaki is due to complete in April 2006. At present AZENCO is carrying out preparatory work in the territory, including the mobilization of the necessary infrastructure for the commencement of the construction-assembly operations.