BAKU, Azerbaijan, February 16. Uzbekneftegaz completed repair work at well No.32 of the Kulbeshkak field (the country’s Bukhara region), a source at the company told Trend.
The Kulbeshkak field was put into operation in 2008.
As a result, an industrial gas flow of 50,000 cubic meters of gas and 1 ton of gas condensate per day was obtained.
A perforation of well No.32 was carried out (1844-1841, 1838-1835, 1833-1831 meters), while in the interval of 1877-1845 meters of the well, a cement bridge was installed.
Earlier in January 2023, Uzbekneftegaz completed repair work at well No.51 of the Kulbeshkak field. As a result, an industrial gas flow of 60,000 cubic meters of gas and 1 ton of gas condensate per day was obtained.