Construction progress in Bahar-Gum Deniz project

Oil&Gas Materials 26 July 2021 12:41 (UTC +04:00)
Construction progress in Bahar-Gum Deniz project

BAKU, Azerbaijan, July 26

By Leman Zeynalova - Trend:

The US Greenfields Petroleum Company, which operates the Bahar-Gum Deniz project in Azerbaijan through its subsidiary BEOC, has published the Q1 2021 results on construction progress, Trend reports.

The table below shows the construction data for Q1:

#

Field/Location

Work Description

Status

Gum Deniz

1

Gum-Deniz,Causeways

Completed hammering of 2 piles out of 10"pipes around 74th bad support in between PLT64-66, connecting works in between the piles on-going

In progress

2

Gum-Deniz,Causeways

In order to install 10x10x600mm metal panels at PLT209, mounting of 1st panel was done, welding of the frame and intermediate sections using 60B2 and 40B2 i-beams is on going.

In progress

3

Gum-Deniz,Causeways

Installation of cable supports along the causway

In progress

4

Gum-Deniz,Causeways PLT9

Hammering of 16" piles due to the widening of the causeway in between the crossroads and PLT9, the 6 / 0.4kV Distribution Unit #13 located at PLT 9 is being installed, installation of panels and connecting to the existing causeway.

In progress

5

Gum-Deniz,OP&TCS, 2000m3

At CS the extension of the emulsion line from the technological tanks to the pumping station from 12 "pipes and the reconstruction of the foundation of 1 SNS 300x300 pump at the oil pumping station were completed. the re-installed pump was connected to the newly constructed 12 "pipeline and the existing 6" outlet line

In progress

Bahar field

6

Bahar, GZU-2

Proceeding the installation of 12"" gas flow line pipe supports along the existing bridge according to the project. Expansion of the existing comb separator area in the south-western part of the working area. Assembling of service areas for installation of Flare and drainage system. Welding of comb separators and pipe fittings, manufactured and shipped in the workshop, is ongoing on the newly installed panels.

In progress

7

Bahar, PLT-196-20

Moved the crew from Bahar PLT196 to Bahar PLT20. Recovery works over well206 at PLT20 prepare for WO operations. Assembling of 4th 10x10m metal plate

In progress

8

Bahar, PLT-196

As for WO operations, construction, installation works completed on the well#196 at PLT 196 of Bahar field

Completed

9

Bahar, PLT-70/106

Repair and installation works over the well#74 at PLTBH 106/70б preparation for WO operations. Installation of 3rd 10x10x600mm metal sheet

In progress

The Bahar Gas Field consists of 45 offshore platforms including a central processing and metering platform to gather the gas for onward transport through a three 12-inch pipelines to the shore-based gas and liquid handling facilities. The platforms, in most cases are built on 24 to 30 pilings each in an average water depth of about 16 metres.

The Gum Deniz Oil Field is located south of the Absheron peninsula, 21 km south of Baku, between Gum Island and the Bahar Gas Field. The Gum Deniz Oil Field extends from onshore Gum Island, which is 2.5 km from the mainland to the south in the Caspian Sea. The Gum Deniz Oil Field is found along the Fatmai–Gum Adasi anticlinal trend which includes the Bahar and Shakh Deniz structures. Oil in the Gum Deniz Oil Field is trapped in a north-south trending structure that is approximately 16 kilometres in length and 3 kilometres in width. The Gum Deniz Oil Field is structurally up-dip from the Bahar Gas Field.

---

Follow the author on Twitter: @Lyaman_Zeyn