BAKU, Azerbaijan, May 5. The Istiglal and Maersk Explorer rigs have already drilled 21 wells in total and completed 19 out of those for the Shah Deniz 2 production and subsequent ramp-up, Trend reports with reference to bp.

“The completed wells include five wells on the North flank, four wells on the West flank, four wells on the East South flank, four wells on the West South flank and two wells on the East North flank. One well on the West South flank and one well on the East North flank were drilled to the final depth and suspended,” the company said.

In the first quarter of 2022, the Shah Deniz Alpha platform rig was on warm stack.

The existing Shah Deniz facilities’ production capacity is currently about 72 million standard cubic metres of gas per day or more than 26 bcma.

During the quarter, the Shah Deniz field continued to provide deliveries of gas to markets in Azerbaijan (to Azerkontrakt), Georgia (to GOGC), Turkey (to BOTAS), to the BTC Company in multiple locations and to buyers in Europe.

Shah Deniz participating interests are: bp (operator – 29.99 percent), LUKOIL (19.99 percent), TPAO (19 percent), SOCAR (14.35 percent), NICO (10 percent) and SGC (6.67 percent).

---