Construction of an additional bunker silo in the territory of the feed plant built in Azerbaijan’s Yalama agro-industrial park will continue next year as well, director of the agropark Zaur Aliyev told Trend Nov. 27.

He reminded that earlier it was expected that construction work in this direction will be completed by the end of this year.

“Construction of an industrial warehouse in the territory of the feed plant began much later than we planned, so we are late with the deadlines for this facility,” said Aliyev. “According to our calculations, the process will take another 3-4 months, and will be completed by April 2019.”

He noted that the feed plant operating in the Yalama agropark produces 13 types of feed, and is intended to cover the needs of local livestock farms.