BP to Expand Capacity of Receiving Gas from Azerbaijani Field

Oil&Gas Materials 1 July 2008 19:17 (UTC +04:00)

Azerbaijan, Baku, 1 July /corr. Trend S.Aliyev / BP Company - technical operator of development project of gas-condensate field of Shah Deniz - will replace separators to receive gas from this field in Sangachal terminal, a Government source said.

The separators are replaced to increase their capacity, the same source said. The capacity of the existing separators was nearly 21mln cu.m per day. This volume is generated from four wells drilled on the field with the platform. Generally seven wells will be drilled with the platform.

Today the gas production from Shah Deniz makes up averagely 21mln cu.m. per day. Of this volume, Turkey receives nearly 10-11mln cu.m per day, and remaining volume is transferred to Azerbaijan, Georgia and as fuel to the pumping stations of Baku-Tbilisi-Ceyhan pipeline.

The contract on development of off-shore Shah Deniz field was signed on 4 June 1996. The sides to the contract are ВР (operator - 25.5%), Statoil (25.5%), SOCAR (10%), LukAgip (10%), NICO (10%), Total (10%), and TPAO (9%).

The gas production on this field began in December 2006. At present gas is transported to Georgia and Turkey via South Caucasus Pipeline. Azerbaijan is also a buyer of gas.

Some 8.6bln cu.m of gas is intended to be produced within the first stage of the development of the field. These volumes will be sold to Azerbaijan, Georgia and Turkey. Within the framework the second stage, realization of which will begin after 2012, the production will be increased up to 20bln cu.m.

The correspondent can be contacted at: [email protected]  