BAKU, Azerbaijan, Jan. 9

By Fakhri Vakilov-Trend:

ERIELL Group international oilfield services completed the next stage of field development in Uzbekistan under the program of measures to increase hydrocarbon production for 2017-2021, in conjunction with Uzbekistan’s Uzbekneftegaz oil and gas company, Trend reports citing the company's statement.

Positive results were achieved in production indicators at the Shurtan, Zevardy and Istmok fields of the Kashkadarya region, four new wells were put into operation, and the construction of loop gas pipelines was completed.

Well No. 325 was commissioned at the Shurtan field of the Shurtan Oil and Gas Directorate, for the successful operation of which a gas pipeline with a diameter of 114x6 mm and a length of 1,431 m was built. The well was connected to an existing gas gathering point (GGP) -15.

In addition, well No. 324 connected to GGP-3, started operating at the field. The commissioning required the construction of a gas pipeline loop with a diameter of 114x6 mm and a length of 1,180 m, the report said.

At the Zevardy field of the Mubarek Oil and Gas Production Directorate, a loop gas pipeline was constructed with a diameter of 114x9 mm and a length of 1,198 m.

Well No. 311 and well No. 11 at the Istmok field were also commissioned and connected to the existing block of input threads - BVN-8. The construction of a loop gas pipeline with a diameter of 114x9 mm and a length of 1,180 m was completed.

This wells, like all previous ones, were connected to an existing gas collection point at the field, the report said.

---