ERIELL Group discloses wells put into operation in several Uzbek regions

Oil&Gas Materials 18 June 2021 21:14 (UTC +04:00)

BAKU, Azerbaijan, June 18

By Klavdiya Romakayeva - Trend:

ERIELL Group put into operation three new wells, improved two wells and connected five wells to electrochemical protection (ECP) in June 2021, Trend reports with reference to ERIELL Group.

According to the information, the mentioned activities were implemented by ERIELL Group together with the structural divisions of Uzbekneftegaz JSC within the framework of the project on measures to increase the production of hydrocarbon raw materials in Uzbekistan for 2017-2021.

Thus, well No. 11 of the Tegermen field of the Mubarek Oil and Gas Production Department was commissioned in the Kashkadarya region. The well flow rate amounted to 243,706 cubic meters per day. The construction of a gas pipeline loop with a diameter of 168 × 6 millimeters and a total length of 525 meters was completed.

Also, well No. 318 of the Zevardy field of the Mubarek oil and gas production department was commissioned in the Kashkadarya region. The construction of a gas pipeline loop with a diameter of 168 × 6 millimeters and a total length of 399 meters was completed.

In the Karakalpakstan Republic, two wells No. 87 of the Shimoliy Berdakh field and No. 25 of the Inam deposit of the Ustyurt Gas Production Department have been improved.

Moreover, well No. 57 of the Khodjikazgan field of the Gazli oil and gas production department was commissioned in the Bukhara region. The construction of a gas pipeline loop with a diameter of 108 × 8 millimeters and a total length of 3318 meters was completed.

In the Gazli region, work was completed to connect wells 1, 2, 10, 11, and 12 of the Andakli field to electrochemical protection (ECP).

---

Follow the author on Twitter: @romakayeva