BAKU, Azerbaijan, Sept. 27
By Fakhri Vakilov – Trend:
The constructors and installers of the Turkmengazupjunchilik association's gas supply department in the Mary region have commissioned a gas pipeline with a length of 24,780 meters, Trend reports referring to the Turkmenbashi complex of oil refineries.
Moreover, a number of sections of the existing gas pipelines have been overhauled.
In addition, the construction of medium and high-pressure gas pipelines is being carried out in the towns and villages of the Mary region.
Recently, after repairs, the specialists of the gasification department commissioned a high-pressure gas pipeline with a length of 3,300 meters, in the villages of the Murgap district of the Mary region. The commissioning of the gas pipeline amounted to $2.7 million.
---
Follow the author on Twitter:@vakilovfaxri