Nearly 80% of equipment for construction of module power plant has been delivered from Finland to Nakhchivan Autonomous Republic, Trend reports wit reference to press service of Azerenerji AO. This equipment is delivered to Nakhchivan via Turkey.
The generators are only left now. Besides, most equipment of ABB, subcontractor to Wartsila construction contractor, has been delivered as well.
Construction of water 5km water line is complete in short, enabling water provision for the plant.
The plant is commissioned late this year.