State Oil Company install new pipeline

Oil&Gas Materials 25 July 2006 15:00 (UTC +04:00)

The State Oil Company of Azerbaijan started installing a new high-pressure gas pipeline within the gas production increase program, Trend reports with reference to SOCAR. The pipeline is installed between Guneshli and Neft Dashari fields from pipelaying vessel Suleymn Vezirov.

This pipeline totals 22 km in length, from which 8.5km is a new line. The pipeline throughput capacity is 2mln m3 of gas a day. The vessel is installing up to 500-700m of line daily.

In case the weather allows, the whole line will be installed in 7-10 days. Upon the pipeline commissioning it will pass up to 1mln m3 of gas a day.