Azerbaijan increases electricity generation

Oil&Gas Materials 7 April 2014 13:44 (UTC +04:00)
Over 6.2 billion kilowatt hours of electricity was generated by power plants of Azerenergy JSC (production and distribution of electricity in Azerbaijan) in Jan.-March 2014.
Azerbaijan increases electricity generation

Baku, Azerbaijan, April 7
By Emil Ismayilov - Trend:

Over 6.2 billion kilowatt hours of electricity was generated by power plants of Azerenergy JSC (production and distribution of electricity in Azerbaijan) in Jan.-March 2014, the JSC said on April 7.

Nearly six billion kilowatt hours of electricity was generated by power plants of Azerenergy JSC in the first quarter of 2013.

The JSC's power plants generated over two billion kilowatt hours of electricity in March 2014 compared to nearly two billion kilowatt hours in March 2013.

In total, Azerenergy JSC produced over 21.5 billion kilowatt hours of electricity in 2013 compared to 21.3 billion kilowatt hours in 2012.

The capacity of power plants owned by Azerenergy JSC exceeds 6,500 megawatt.