Georgia, Tbilisi, June 19 / Trend , N. Kirtskhalia/
North-South gas pipeline will be overhauled by four companies as a part of the third stage. Fund of Millennium Challenge Corporation has already signed contracts with Seacor Environmental Services, Hidrienergomontaj, Ferry and New Enerji Tbilisi.
Seacor Environmental Services will perform the overhaul at $215,948 which includes shore protection at White Aragavi River.
Under the contract, Hidrienergomontaj will replace and consolidate 1,200-1,700 millimeters of gas pipeline at the junction of Kabarjino and Belaya Rivers. The contact with the company costs 2,102, 987 lari.
Ferry will overhaul section of the gas pipeline lying along Baydar River and will also install and connect cranes at gas pipelines of various diameters at this section. The company will charge 942,097 lari.
The contract with New Enerji Tbilisi costs 703, 620 lari. The company will replace 700-millimeter gas pipeline at the junction of Snostskali River. The overhaul, great part of which will be performed in mountainous sections of Kazbek region, will end by late October.