BP updates on progress in Azeri Central East project

Oil&Gas Materials 17 November 2020 11:54 (UTC +04:00)
BP updates on progress in Azeri Central East project

BAKU, Azerbaijan, Nov.17

By Leman Zeynalova – Trend:

During the third quarter, fabrication activities on the topsides and drilling facilities for the Azeri Central East (ACE) platform continued at the fabrication yard in Bibi-Heybat, Trend reports with reference to BP.

The ACE Project represents the next stage of development in the Azeri-Chirag-Gunashli (ACG) Contract Area.

“The latest activities include the commencement of the major lift programme despite the disruption caused by COVID-19, the arrival of the drilling derrick at the yard, with all three sections of the derrick already safely offloaded from the barge and positioned at the site’s construction location. Construction of the drilling modules is currently ongoing.

At the Heydar Aliyev Baku Deepwater Jackets factory (BDJF) the pin piles have been completed, successfully loaded out and driven into the seabed ready to receive the platform jacket. The jacket fabrication continues, as does the work on the subsea structures.

Engineering and procurement works remain on track to support the first production from the ACE project in 2023, with the larger equipment now moving from the suppliers into Azerbaijan,” the company said.

---

Follow the author on Twitter: @Lyaman_Zeyn