Construction progress at Gum Deniz field – latest data

Oil&Gas Materials 25 December 2020 10:44 (UTC +04:00)
Construction progress at Gum Deniz field – latest data

BAKU, Azerbaijan, Dec.25

By Leman Zeynalova – Trend:

The construction progress at Azerbaijan’s Gum Deniz oil field has been provided by the US Greenfields Petroleum Company, which operates the Bahar-Gum Deniz project in Azerbaijan through its subsidiary BEOC, Trend reports with reference to the company.

The table below shows the ongoing and completed construction works at the field as of October 2020:

Gum-Deniz,Causeways,Entrance road

Repairs & istallation of 20" production pipeline supports along the entrance road and on the causeways in the area between 62-235 and 66-450

in progress

Gum-Deniz,PLT232 at Causeways

Hammering of 4 piles 10" each for repair of road section in between 160B and PLT232 at the causways & hammering of 2 piles for 160-160B, intermidiate connection works.

in progress

Gum-Deniz,Causeways PLT9

Connection of 600mm i-beam with 10x10 panels installed on the causways' piles for the widening of the vehicle pass at the causeway in between the crossroads and PLT9 where 6 / 0.4kV Distribution Unit No. 13 located.

in progress

Gum-Deniz, PLT9

Piles hammering and linking for road repair at PLT9 and area between PLT9 and road to the base.

completed

Gum-Deniz, Causeways, in between PLT235-64

As a part of repair job of the road in between PLT235 and PLT64, hammering and connection of 10" piles around bad piles #36-40

in progress

Gum-Deniz, PLT2

Shifting the pedestal from the well#372 onto the well#202 with UPT 1-150 pulling unit on it. The repair works on the derrick of UPT1-150 pulling unit done

completed

The Gum Deniz Oil Field is located south of the Absheron peninsula, 21 km south of Baku, between Gum Island and the Bahar Gas Field. The Gum Deniz Oil Field extends from onshore Gum Island, which is 2.5 km from the mainland to the south in the Caspian Sea. The Gum Deniz Oil Field is found along the Fatmai–Gum Adasi anticlinal trend which includes the Bahar and Shakh Deniz structures. Oil in the Gum Deniz Oil Field is trapped in a north-south trending structure that is approximately 16 kilometres in length and 3 kilometres in width. The Gum Deniz Oil Field is structurally up-dip from the Bahar Gas Field.

---