BAKU, Azerbaijan, Aug.14

By Klavdiya Romakayeva - Trend:

Uzbekneftegaz JSC from January through July 2021 has drilled 101 wells, overhauled 405 wells and built 39 technological facilities, Trend reports citing the press service of Uzbekneftegaz.

It is reported that as a result of the timely implementation of these measures, an additional 1,800.1 million cubic meters of natural gas and 31.7 thousand tons of gas condensate were produced.

In addition, as a result of the implementation of the above geological and technical measures and the systematic operation of existing wells, the implementation of Uzbekneftegaz JSC's targets for oil and gas production and processing in 7M2021 amounted to:

Natural gas - 19.6 million cubic meters;

Oil - 68,900 tons, exceeding the plan by 6.9 percent;

Condensate - 821,800 tons, exceeding the plan by 1.6 percent;

Sulfur - 154,000 tons, exceeding the plan by 28.7 percent;

Polyethylene - 74,400 tons, exceeding the plan by 5.8 percent;

Gasoline - 508,200 tons, exceeding the plan by 26.1 percent;

Diesel fuel - 167,000 tons, exceeding the plan by55.2 percent.

---

Follow the author on Twitter: @romakayeva