BAKU, Azerbaijan, August 12. Uzbekneftegaz JSC completed repair and insulation work at well No.16 of the Doyakhotin field (country’s Bukhara region), Trend reports citing the press service of the company.
As a result of the work carried out, an industrial gas flow of 100,000 cubic meters of gas and 1 ton of gas condensate per day was obtained.
The Doyakhotin gas condensate field is located on the territory of the Karakul district of the Bukhara region and was put into operation in 2004.
Previously, Uzbekneftegaz JSC conducted geophysical research at well No.42 of the Severny Berdak field (country’s Republic of Karakalpakstan).
As a result of the work carried out, an industrial gas flow of 133,000 cubic meters of gas and 1.5 ton of gas condensate per day was obtained.
---