A new stage has begun in the reconstruction of the Azerbaijani railways, Nadir Azmammadov, spokesman for the Azerbaijan Railways CJSC, told Trend.
Railway section to be overhauled in Azerbaijani western direction

Baku, Azerbaijan, Nov. 6

Trend:

A new stage has begun in the reconstruction of the Azerbaijani railways, Nadir Azmammadov, spokesman for the Azerbaijan Railways CJSC, told Trend.

A 600 kilometer-railway section in the direction of Baku-Boyuk Kesik will be overhauled.

He said that the work is being conducted by the newly established specialized railroad department No 5 under the Azerbaijani Railways CJSC.

The overhaul began at a railway section of the Bilajari station.

An agreement was signed with the Czech contractor of the Azerbaijan Railways - Moravia Steel company to implement the second phase of the Azerbaijani railway reconstruction project on April 14, 2015.

The agreement is a supplement to the export contract on logistics and overhaul of a 600-kilometer Baku-Boyuk Kesik railway section.

The company repaired a 317 kilometer Baku-Boyuk Kesik railway section in December 2013. The work was carried out as part of the "State program on development of the Azerbaijani railway system in 2010-2014" through a loan worth 215 million euros allocated by the Czech "Exim Bank".