Barmek doesn't fulfill even little part of liabilities under investment contract, Azerenerji

Oil&Gas Materials 14 March 2006 18:55 (UTC +04:00)

Over the 4 years of its work Barmek, the Energy Distribution Company, did not fulfill even the little part of its liabilities under the investment contract, Trend reports referring to a news release spread by Azerenerji JSC.

The projects on construction of the 110KV Narimanov substation in the Yasamal district, Gara Sheher - Katayi district, Idman Sarayi - Nasimi district, Icheri Sheher - Sbayil distcrt have not been implemented yet.

The rehabilitation work on the 35-KV electricity transmission line proceeding from the repaired substations of Barmek is also unsatisfied. Old repaired transformers were installed at the station as new. The expenses on the work were included into the investment accounts, while they were envisaged in retail price of energy.